We were given an estimated 6 weeks for bricks to be completed. A month of delays and the only reason when weather couldn't be used as an excuse was that the brickie was slow but good. Seriously!? Sigh...it was finally finished this Tuesday the 23rd.
SS advised fascia and gutter will be completed today. Roof tiles will be completed Monday or Tuesday next week along with the solar panels.
SS assured the roof trusses and frame carpentry issues will be repaired before lining is installed.